Commuter and Long DistanceTrains Development Project to serve as Feeder for Mass Rapid Transit System in Bangkok and Suburban Area


Location :
Bangkok and suburbs of Bangkok
Client :
Office of Transport and Traffic Policy and Planning (OPT)
Project Value :
Baht 110,000 million
Commencement and Completion :
February 2005 – August 2006
Project scope :

The project aims to make improvements to the existing 4 railway lines, including 1) Rangsit – Baan Pachee: 60 km, 2) Makkason – Chachoung Sao: 50 km, 3) Talingchan – Nakorn Pathom: 43 km and 4) Mahachai – Paktor: 56 km The railway track upgrading includes installation of new tracks where required, installation of lighting system, upgrading of signaling and Communication systems.

Accomplishments :
  • •  Reviewed previous Feasibility Study and related studies
  • •  Conducted a detailed site investigation
  • •  Gathered understanding of existing condition
  • •  Conducted Environment Impact Assessment study
  • •  Developed Detailed Design and construction specifications for the improvement of specific railway line