Double Track Railway Project; East Coast Line: Chachoengsao – Klong Sip Kao - Kaeng Khoi Route


Location :
Chachoengsao province
Client :
State Railway of Thailand
Project Value :
Baht 10,232.88 million
Commencement and Completion :
March 2016–February 2019
Project scope :

The double track railway project involves construction of a new line of railway along exist line. The project route starting from Chachoengsao station to Wiharndang station; total 78 km, from Bui Yai station to Kaeng Khoi station; total 19 km, and from Wiharndang station up to the approaching Bui Yai station; total 9 km. Construction of other railway infrastructure comprises 3 chord lines at 3 junction stations i.e. Chachoengsao, Kaeng Khoi and Baan Phachee; total length 7.1 km, signaling system and telecommunication system along the project route includes 3 chord lines, reinforced concrete railway bridges, reinforced concrete flyover bridges across the railway track and a 1.2 km single-track railway tunnel runs along the side of existing railway tunnel which runs through the Putthachai mountain. 

Accomplishments :
Services provided include:
  • •  Construction management
  • •  Project management and coordination
  • •  Construction Supervision
  • •  Monitoring project quality assurance and contract administration
  • •  Project safety management
  • •  Providing technical supporting on testing and handing over of a completed works
  • •  Contract administration and claims management
  • •  Cost and scheduling control

Back to Our Projects